Putra Heights Interchange
Aerial View of Putra Heights Interchange and Toll Plaza from helicopter.

Tol Plaza Putra Heights
Penyerahan Kunci Bagi Tol Plaza Putra Heights Pada  12 Feb 2009 Kepada PLUS

Selayang Project
The Project  of Selayang.



Welcome to visit Iswarabena Sdn. Bhd. website

Current Project
No.WORK DESCRIPTION /PROJECTCLIENTCONTRACT VALUE
(RM)
CONTRACT PERIOD
1.Cadangan Merekabentuk, Membina dan Menyiapkan 1422 Unit Rumah Berkembar Satu Tingkat Dan Kerja-Kerja Infrastruktur Yang Berkaitan Untuk Penempatan Semula Setinggan Bukit Botak (Taman Selayang Mutiara), Bandar Baru Selayang, Mukim Batu, Daerah Gombak, Kuala Selangor, Selangor Darul Ehsan.

PKNS INFRA

BERHAD

123,500,000.0011.08.10  
to   
10.05.12
2.Proposed Sungai Buaya Interchange and Toll PlazaPLUS86,550,000.00

14.06.2011
to
13.06.2013

3.  Menaiktaraf Jalan Muar – Tangkak – Segamat, Johor (Fasa 1 : Segamat – Tangkak) Pakej 1BJKR150,000,000.00

01.11.2011
to
04.11.2013

 


Completed Project
No.WORK DESCRIPTION /PROJECTCLIENTCONTRACT
VALUE
(RM)
CONTRACT PERIODDATE COMPLETION
1.Propose design, build, testing commissioning and maintainance of Putra Height interchange and toll plaza at KM 13.2 North South link expressway for sime uep Heights Sdn. Bhd.

PKNS INFRA BERHAD 61,780,000.00

15.03.07
to
14.01.09

09.01.09
2.Kerja-kerja menaiktaraf Tiga(3) Jalan Ladang di Wilayah III, Mada.DAMAI SETIA SDN. BHD.4,943,300.00

10.12.08
to
15.09.09

30.04.09
3.Cadangan pembinaan jambatan dari simpang panchor pengkalan Datu, Mukim Panchor, Daerah Kemumin, Kota Bahru, Kelantan.DAMAI SETIA SDN. BHD.9,040,000.00

17.02.09
to
14.08.10

31.10.09
4.Construction of roadworks, roadside drain, water reticulation and sewer reticulation (package 4) at proposed intergrated township development of Bandar Bukit Raja (stage 1), Mukim Kapar, Daerah Klang, Selangor Darul Ehsan.PKNS INFRA BERHAD21,945,336.0024.09.08
to
23.12.09
23.11.2009
5.Proposed Design and Build of a New Pumping Station and Reticulation Works Including Related Works for the Subang Jaya City Centre (SJCC) Development at Subang Jaya for Sime UEP Centre Sdn BhdSIME UEP
CENTRE SDN BHD
11,597,000.00

08.04.10
to
07.02.11

15.09.2010
6.Proposed Construction and Completion of Infrastructure Works and TNB Substation At Zone 6A Development Of Nilai impian & Nilai Utama, Mukim Setul, Daerah Seremban, Negeri Sembilan darul Khusus NEGARA PROPERTIES REALTY SDN BHD10,992,200.0024.02.10  
to   
01.12.10
28.11.2010
7.Proposed PavementRehabilitation And Associated Wprks At KM 32.0 – KM 29.7 Southbound, Along Malaysia – Singapura Second Crossing, Section S5PLUS3,439,300.0014.06.10
to   
04.11.10
01.11.2010
8.Senai – Pasir Gudang – Desaru Expressway Package 3C/6 (480mm ALTERNATIVE DESIGN PAVEMENT)RANHILL ENGINEERS AND CONSTRUCTOR SDN BHD21,945,336.0009.06.09
to
31.01.11
31.01.2011
9.The execution and completion of Mosque for the Asian Institute of Medicine Science and Technology University Mukim Semeling, Daerah Kuala Muda,Kedah Darul Aman.MIED CAPITAL
SDN BHD
3,889,336.0910.03.10
to  
12.01.12
30.03.2012
10.Cadang Membina Jalan Keluar Masuk Di KM 18.5 Lebuhraya Persekutuan (Arah Kuala Lumpur)Bandar Glenmarie Daerah Petaling Untuk Bisraya. Sdn Bhd Shell Trading Malaysia Sdn Bhd Dan Bonus Saujana Sdn BhdMOHD ASBI &
ASSOCIATES
6,914,820.0005.07.10
to
03.01.11
27.03.2012
11.Proposed Bukit Gambir Interchange and Toll Plaza
(Phase 1 – Advanced Earthworks)

PLUS
38,119,920.0012.08.10 
to  
10.08.11
10.02.2012